Move management, for London Quadrant

We had very little time to turn this project around and it was vital that it ran smoothly

Project remit

Dismantle and package 110 existing Herman Miller workstations, chairs,screens and storage. Move from a building in East London to a new building in South London. All furniture to be unpacked and re- installed over various floors. The project was completed inside 10 days to minimise the clients downtime

Project location

South London

Client comment

We had very little time to turn this project around and it was vital that it ran smoothly. Having used JS for the last 3 years, we felt that they would be able meet our deadline. With their hands on approach and attention to detail the project was completed on time. We look forward to working with them in the future.
– Richard Wilson – Facilities Team Leader